Skip to content
Worked Examples · Example 15

Q.A person has undertaken a construction job. The probabilities are 0.65 that there will be a strike, 0.80 that the construction job will be completed on time if there is no strike, and 0.32 that the construction job will be completed on time if there is a strike. Determine the probability that the construction job will be completed on time.

Bihar BsebTextbookSubjective· 5mImportance★★★★★
39% · 64/165 Questions
✓ Free question

Using the law of total probability, we split the event "completed on time" into two mutually exclusive cases (strike vs. no strike). The overall probability is 0.65×0.32+0.35×0.80=0.4880.65 \times 0.32 + 0.35 \times 0.80 = 0.488, or 0.488.

This is a classic law of total probability problem. When an event (here, "job completed on time") can happen under two different conditions (strike or no strike), we cannot just average the conditional probabilities — we must weight each by how likely that condition is.

The key insight: the two conditions (strike, no strike) are mutually exclusive and cover all possibilities. So the total probability of completion is the sum of:

  • Probability of completion given a strike, times the probability of a strike.
  • Probability of completion given no strike, times the probability of no strike.

Let’s define events clearly:

  • SS: there is a strike.
  • CC: the construction job is completed on time.

We are given:

  • P(S)=0.65P(S) = 0.65
  • P(C∣Sc)=0.80P(C \mid S^c) = 0.80 (completed on time given no strike)
  • P(C∣S)=0.32P(C \mid S) = 0.32 (completed on time given strike)

We need P(C)P(C).

  1. Find the probability of no strike. Since SS and ScS^c are complementary:

P(Sc)=1−P(S)=1−0.65=0.35P(S^c) = 1 - P(S) = 1 - 0.65 = 0.35

  1. Apply the law of total probability. The event CC can be written as:

C=(C∩S)∪(C∩Sc)C = (C \cap S) \cup (C \cap S^c)

Since SS and ScS^c are disjoint, the two intersections are also disjoint. Therefore:

P(C)=P(C∩S)+P(C∩Sc)P(C) = P(C \cap S) + P(C \cap S^c)

  1. Rewrite each intersection using conditional probability. By definition: P(C∩S)=P(S)⋅P(C∣S)P(C \cap S) = P(S) \cdot P(C \mid S) and P(C∩Sc)=P(Sc)⋅P(C∣Sc)P(C \cap S^c) = P(S^c) \cdot P(C \mid S^c). So:

P(C)=P(S)⋅P(C∣S)+P(Sc)⋅P(C∣Sc)P(C) = P(S) \cdot P(C \mid S) + P(S^c) \cdot P(C \mid S^c)

  1. Substitute the given numbers.

P(C)=(0.65)(0.32)+(0.35)(0.80)P(C) = (0.65)(0.32) + (0.35)(0.80)

  1. Calculate each term.

    • 0.65×0.32=0.2080.65 \times 0.32 = 0.208
    • 0.35×0.80=0.2800.35 \times 0.80 = 0.280

    Adding:

P(C)=0.208+0.280=0.488P(C) = 0.208 + 0.280 = 0.488

Watch out

A common mistake is to simply average 0.32 and 0.80, getting 0.56. That would be correct only if strike and no strike were equally likely (each 0.5). But here, a strike is more likely (0.65), so the overall probability is pulled closer to 0.32 than to 0.80.

Tip

Think of this as a weighted average: the weights are the probabilities of the conditions. The formula P(C)=P(S)P(C∣S)+P(Sc)P(C∣Sc)P(C) = P(S)P(C|S) + P(S^c)P(C|S^c) is just a weighted mean of the two conditional probabilities.

✓Final answer

The probability that the construction job will be completed on time is 0.488\boxed{0.488}.

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.