Skip to content
Exercises · Q25
Q.

The following table shows the total cost schedule of a firm. What is the total fixed cost schedule of this firm? Calculate the TVCTVC, AFCAFC, AVCAVC, SACSAC and SMCSMC schedules of the firm.

QQTCTC (Rs)
010
130
245
355
470
590
6120
CBSENCERTSubjective· 5mImportance★★★★★
68% · 25/37 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

This problem requires understanding and applying various short-run cost concepts to a given total cost schedule. The key is to first identify total fixed cost (TFC) at zero output, then derive total variable cost (TVC), and subsequently calculate average fixed cost (AFC), average variable cost (AVC), short-run average cost (SAC), and short-run marginal cost (SMC) using their respective formulas.

In the short run, a firm's total costs are divided into two main categories: fixed costs and variable costs. Understanding these distinctions is crucial for analyzing a firm's production decisions and profitability. Fixed costs are those expenses that do not change with the level of output in the short run, such as rent for factory space or salaries of permanent administrative staff. These costs are incurred even if the firm produces zero output. Variable costs, on the other hand, are expenses that vary directly with the level of output, such as raw material costs or wages for production workers. As output increases, variable costs increase, and as output decreases, they fall.

The total cost (TC) at any level of output is simply the sum of total fixed cost (TFC) and total variable cost (TVC). From these total cost figures, we can derive various per-unit costs, which provide insights into the efficiency of production. Average fixed cost (AFC) tells us the fixed cost per unit of output, average variable cost (AVC) tells us the variable cost per unit, and short-run average cost (SAC) gives the total cost per unit. Finally, short-run marginal cost (SMC) measures the change in total cost (or total variable cost) resulting from producing one additional unit of output.

Let's calculate each of these schedules step-by-step using the provided total cost data.

1. Total Fixed Cost (TFC) Schedule

Total Fixed Cost (TFC) is the cost incurred by the firm even when no output is produced. Looking at the given table, when the quantity (QQ) is 0, the Total Cost (TCTC) is Rs 10. This Rs 10 represents the fixed cost of the firm, as it must be paid regardless of production. Since fixed costs do not change with output in the short run, the TFC will remain constant at Rs 10 for all levels of output.

TFC=TC when Q=0TFC = TC \text{ when } Q = 0

Therefore, the TFC schedule is:

QQTFCTFC (Rs)
010
110
210
310
410
510
610

2. Total Variable Cost (TVC) Schedule

Total Variable Cost (TVC) is the portion of total cost that changes with the level of output. It can be calculated by subtracting the Total Fixed Cost (TFC) from the Total Cost (TC) at each level of output.

TVC=TC−TFCTVC = TC - TFC

Let's calculate TVC for each output level:

  • For Q=0Q=0: TVC=10−10=0TVC = 10 - 10 = 0
  • For Q=1Q=1: TVC=30−10=20TVC = 30 - 10 = 20
  • For Q=2Q=2: TVC=45−10=35TVC = 45 - 10 = 35
  • For Q=3Q=3: TVC=55−10=45TVC = 55 - 10 = 45
  • For Q=4Q=4: TVC=70−10=60TVC = 70 - 10 = 60
  • For Q=5Q=5: TVC=90−10=80TVC = 90 - 10 = 80
  • For Q=6Q=6: TVC=120−10=110TVC = 120 - 10 = 110

3. Average Fixed Cost (AFC) Schedule

Average Fixed Cost (AFC) is the fixed cost per unit of output. It is calculated by dividing Total Fixed Cost (TFC) by the quantity of output (QQ). As output increases, the fixed cost is spread over more units, so AFC continuously declines.

AFC=TFCQAFC = \frac{TFC}{Q}

Watch out

AFC is undefined at Q=0Q=0 because division by zero is not possible.

Let's calculate AFC for each output level:

  • For Q=0Q=0: AFCAFC is undefined.
  • For Q=1Q=1: AFC=101=10AFC = \frac{10}{1} = 10
  • For Q=2Q=2: AFC=102=5AFC = \frac{10}{2} = 5
  • For Q=3Q=3: AFC=103≈3.33AFC = \frac{10}{3} \approx 3.33
  • For Q=4Q=4: AFC=104=2.5AFC = \frac{10}{4} = 2.5
  • For Q=5Q=5: AFC=105=2AFC = \frac{10}{5} = 2
  • For Q=6Q=6: AFC=106≈1.67AFC = \frac{10}{6} \approx 1.67

4. Average Variable Cost (AVC) Schedule

Average Variable Cost (AVC) is the variable cost per unit of output. It is calculated by dividing Total Variable Cost (TVC) by the quantity of output (QQ).

AVC=TVCQAVC = \frac{TVC}{Q}

Watch out

AVC is undefined at Q=0Q=0.

Let's calculate AVC for each output level:

  • For Q=0Q=0: AVCAVC is undefined.
  • For Q=1Q=1: AVC=201=20AVC = \frac{20}{1} = 20
  • For Q=2Q=2: AVC=352=17.5AVC = \frac{35}{2} = 17.5
  • For Q=3Q=3: AVC=453=15AVC = \frac{45}{3} = 15
  • For Q=4Q=4: AVC=604=15AVC = \frac{60}{4} = 15
  • For Q=5Q=5: AVC=805=16AVC = \frac{80}{5} = 16
  • For Q=6Q=6: AVC=1106≈18.33AVC = \frac{110}{6} \approx 18.33

5. Short-run Average Cost (SAC) Schedule

Short-run Average Cost (SAC), also known as Average Total Cost (ATC), is the total cost per unit of output. It can be calculated by dividing Total Cost (TC) by the quantity of output (QQ), or by summing Average Fixed Cost (AFC) and Average Variable Cost (AVC).

SAC=TCQorSAC=AFC+AVCSAC = \frac{TC}{Q} \quad \text{or} \quad SAC = AFC + AVC

Watch out

SAC is undefined at Q=0Q=0.

Let's calculate SAC for each output level:

  • For Q=0Q=0: SACSAC is undefined.
  • For Q=1Q=1: SAC=301=30SAC = \frac{30}{1} = 30 (or 10+20=3010 + 20 = 30)
  • For Q=2Q=2: SAC=452=22.5SAC = \frac{45}{2} = 22.5 (or 5+17.5=22.55 + 17.5 = 22.5)
  • For Q=3Q=3: SAC=553≈18.33SAC = \frac{55}{3} \approx 18.33 (or 3.33+15=18.333.33 + 15 = 18.33)
  • For Q=4Q=4: SAC=704=17.5SAC = \frac{70}{4} = 17.5 (or 2.5+15=17.52.5 + 15 = 17.5)
  • For Q=5Q=5: SAC=905=18SAC = \frac{90}{5} = 18 (or 2+16=182 + 16 = 18) …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.