Numerical Questions · Q4
Q.Berlia Ltd. Purchased a second hand machine for ₹ 56,000 on July 01, 2015 and spent ₹ 24,000 on its repair and installation and ₹ 5,000 for its carriage. On September 01, 2016, it purchased another machine for ₹ 2,50,000 and spent ₹ 10,000 on its installation.
(a) Depreciation is provided on machinery @10% p.a on original cost method annually on December 31. Prepare machinery account and depreciation account from the year 2015 to 2018.
(b) Prepare machinery account and depreciation account from the year 2011 to 2018, if depreciation is provided on machinery @10% p.a. on written down value method annually on December 31.
Sikkim CbseNCERTSubjective· 5mImportance★★★★★est
47% · 26/55 Questions
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →Two machines are depreciated under (a) SLM on original cost and (b) WDV method, both @10% p.a., books closing 31 December. Depreciation is debited to Depreciation A/c and credited to Machinery A/c each year (the machinery account itself is reduced). Machine I cost = 56,000 + 24,000 + 5,000 = ₹85,000 (01.07.2015); Machine II cost = 2,50,000 + 10,000 = ₹2,60,000 (01.09.2016). First-year charges are prorated for months in use.
(a) SLM — 10% on Original Cost
Machinery Account
| Particulars | Amount (₹) | Particulars | Amount (₹) |
|---|---|---|---|
| 2015 Jul 1 To Bank A/c (M-I) | 85,000 | 2015 Dec 31 By Depreciation A/c | 4,250 |
| 2015 Dec 31 By Balance c/d | 80,750 | ||
| 85,000 | 85,000 | ||
| 2016 Jan 1 To Balance b/d | 80,750 | 2016 Dec 31 By Depreciation A/c (8,500 + 8,666.67) | 17,166.67 |
| 2016 Sep 1 To Bank A/c (M-II) | 2,60,000 | 2016 Dec 31 By Balance c/d | 3,23,583.33 |
| 3,40,750 | 3,40,750 | ||
| 2017 Jan 1 To Balance b/d | 3,23,583.33 | 2017 Dec 31 By Depreciation A/c (8,500 + 26,000) | 34,500 |
| 2017 Dec 31 By Balance c/d | 2,89,083.33 | ||
| 3,23,583.33 | 3,23,583.33 | ||
| 2018 Jan 1 To Balance b/d | 2,89,083.33 | 2018 Dec 31 By Depreciation A/c (8,500 + 26,000) | 34,500 |
| 2018 Dec 31 By Balance c/d | 2,54,583.33 | ||
| 2,89,083.33 | 2,89,083.33 | ||
| 2019 Jan 1 To Balance b/d | 2,54,583.33 |
Depreciation Account (SLM)
| Particulars | Amount (₹) | Particulars | Amount (₹) |
|---|---|---|---|
| 2015 Dec 31 To Machinery A/c | 4,250 | 2015 Dec 31 By Profit & Loss A/c | 4,250 |
| 2016 Dec 31 To Machinery A/c | 17,166.67 | 2016 Dec 31 By Profit & Loss A/c | 17,166.67 |
| 2017 Dec 31 To Machinery A/c | 34,500 | 2017 Dec 31 By Profit & Loss A/c | 34,500 |
| 2018 Dec 31 To Machinery A/c | 34,500 | 2018 Dec 31 By Profit & Loss A/c | 34,500 |
(b) WDV — 10% on Written Down Value
Machinery Account
| Particulars | Amount (₹) | Particulars | Amount (₹) |
|---|---|---|---|
| 2015 Jul 1 To Bank A/c (M-I) | 85,000 | 2015 Dec 31 By Depreciation A/c | 4,250 |
| 2015 Dec 31 By Balance c/d | 80,750 | ||
| 85,000 | 85,000 | ||
| 2016 Jan 1 To Balance b/d | 80,750 | 2016 Dec 31 By Depreciation A/c (8,075 + 8,666.67) | 16,741.67 |
| 2016 Sep 1 To Bank A/c (M-II) | 2,60,000 | 2016 Dec 31 By Balance c/d | 3,24,008.33 |
| 3,40,750 | 3,40,750 | ||
| 2017 Jan 1 To Balance b/d | 3,24,008.33 | 2017 Dec 31 By Depreciation A/c (7,267.50 + 25,133.33) | 32,400.83 |
| 2017 Dec 31 By Balance c/d | 2,91,607.50 | ||
| 3,24,008.33 | 3,24,008.33 | ||
| 2018 Jan 1 To Balance b/d | 2,91,607.50 | 2018 Dec 31 By Depreciation A/c (6,540.75 + 22,620) | 29,160.75 |
| 2018 Dec 31 By Balance c/d | 2,62,446.75 | ||
| 2,91,607.50 | 2,91,607.50 | ||
| 2019 Jan 1 To Balance b/d | 2,62,446.75 |
Depreciation Account (WDV)
| Particulars | Amount (₹) | Particulars | Amount (₹) |
|---|---|---|---|
| 2015 Dec 31 To Machinery A/c | 4,250 | 2015 Dec 31 By Profit & Loss A/c | 4,250 |
| 2016 Dec 31 To Machinery A/c | 16,741.67 | 2016 Dec 31 By Profit & Loss A/c | 16,741.67 |
| 2017 Dec 31 To Machinery A/c | 32,400.83 | 2017 Dec 31 By Profit & Loss A/c | 32,400.83 |
| 2018 Dec 31 To Machinery A/c | 29,160.75 | 2018 Dec 31 By Profit & Loss A/c | 29,160.75 |
Working Notes …
Unlock everything free for 14 days
- Full step-by-step solutions
- Concept-first explanations
- Methods, shortcuts & mistakes
- PYQ mapping + timed mock tests
Full access for 14 days. No credit card required.