- If the distance of a point from the points and are in the ratio , then find the locus of the point. OR
- Construct the network for the project whose activities are given below.
| Activity | 0-1 | 1-2 | 1-3 | 2-4 | 2-5 | 3-4 | 3-6 | 4-7 | 5-7 | 6-7 |
|---|---|---|---|---|---|---|---|---|---|---|
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the Earliest Start Time (EST), Earliest Finish Time (EFT), Latest Start Time (LST) and Latest Finish Time (LFT) of each activity. Determine the critical path and the project completion time.
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →(a) yields . (b) The critical path is with completion time weeks.
Part (a) — Locus of the point.
Let the moving point be , with and . Given , so .
Step 1 — Write the squared distances.
Step 2 — Expand.
Step 3 — Bring all terms to one side.
So the locus is .
Part (b) — Network analysis (CPM).
Compute earliest event times (forward pass) and latest event times (backward pass) with durations 0-1:3, 1-2:8, 1-3:12, 2-4:6, 2-5:3, 3-4:3, 3-6:8, 4-7:5, 5-7:3, 6-7:8.
Forward pass (earliest event times):
Backward pass (latest event times):
Activity table (EST , EFT , LFT , LST ):
| Activity | EST | EFT | LST | LFT | Float | |
|---|---|---|---|---|---|---|
| 0-1 | 3 | 0 | 3 | 0 | 3 | 0* |
| 1-2 | 8 | 3 | 11 | 12 | 20 | 9 |
Unlock everything free for 14 days
- Full step-by-step solutions
- Concept-first explanations
- Methods, shortcuts & mistakes
- PYQ mapping + timed mock tests
Full access for 14 days. No credit card required.