Q.A worker is given a Time Allowed of 8 hours for a job at a Time Rate of ₹18 per hour, but actually takes 9 hours to complete it. Calculate the worker's Total Earnings under

(a) the Halsey Scheme and
(b) the Rowan Scheme.
West Bengal WbchseTextbookSubjectiveImportance★★★★★est
89% · 8/9 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Time Saved = Time Allowed − Time Taken = 8 − 9 = −1 hour, which is NEGATIVE — but a Premium Bonus Scheme never treats a negative time-saved figure as a penalty. By convention, whenever Time Taken equals or exceeds Time Allowed, Time Saved is simply taken as Nil, and no bonus is paid under either scheme; the worker is not penalised for taking longer than standard, only denied the extra bonus.

  1. Halsey Scheme: Bonus = 50% × Nil × ₹18 = ₹0. Total Earnings = Time Taken × Time Rate = 9 × ₹18 = ₹162.
  2. Rowan Scheme: Bonus = (Nil ÷ 8) × 9 × ₹18 = ₹0. Total Earnings = 9 × ₹18 = ₹162. …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.