Q.A agrees to supply 100 bags of wheat to B on 1st March. On 15th February, A informs B that he will not be able to supply the wheat at all. What type of breach has occurred, and what options does B have?

Puducherry TnboardTextbookSubjectiveImportance★★★★★est
69% · 9/13 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

A's declaration on 15th February — well before the agreed delivery date of 1st March — that he will not supply the wheat at all, is a clear express anticipatory breach of contract, since it is made before the time fixed for performance has arrived.

B's options on an anticipatory breach:

  1. Treat the contract as discharged immediately — B can rescind the contract at once (on 15th February itself) and sue A for damages for breach, without needing to wait until 1st March. …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.