Exercise 2.3 · Q6

Q.100 persons begin to work together on a project which was expected to be completed in 40 days. But after few days 40 persons left. As a result, the project got delayed by 10 days. How many days after the commencement of the project did the 40 persons left?

Yanam CbseNCERTSubjective· 3mImportance★★★★★est
57% · 40/70 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Using total work in person-days and splitting it between the 25-day full-strength phase and the remaining 60-person phase (to a 50-day total) shows the 40 workers left after 25 days.

Total work (in person-days) == number of workers ×\times planned days. If the workforce changes partway through, total work == (workers before change ×\times days before change) ++ (workers after change ×\times days after change).

Given: 100100 persons planned to finish in 4040 days; after xx days, 4040 persons leave (leaving 6060); the project is delayed by 1010 days, so it actually finishes in 40+10=5040+10=50 days.

  1. Total work required:

W=100×40=4000 person-daysW = 100 \times 40 = 4000\ \text{person-days}

  1. Work done in the first xx days by 100100 people: 100x100x. Work done in the remaining (50−x)(50-x) days by 6060 people: 60(50−x)60(50-x). Together they equal the total work: …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.