Question 68 of 81
Q.From the following information, calculate the earnings of workers A and B under straight piece-rate system :
Normal rate per hour : Rs.1,800
Standard time per unit : 20 seconds
Worker A produces 240 units in one hour and Worker B produces 390 units in one hour.
ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2023Subjective· 8mImportance★★★★★est
84% · 68/81 Questions
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →Piece rate = Rs.10/unit; A earns Rs.2,400 and B earns Rs.3,900 under straight piece-rate.
Step 1 — Find the standard output per hour (standard time per unit = 20 seconds):
- 1 hour = 60 × 60 = 3,600 seconds.
- Standard output per hour = 3,600 ÷ 20 = 180 units per hour.
Step 2 — Find the piece rate per unit (normal rate per hour = Rs.1,800):
- Piece rate = Normal rate per hour ÷ Standard units per hour = 1,800 ÷ 180 = Rs.10 per unit.
Step 3 — Earnings under straight piece-rate (Earnings = Units produced × Piece rate):
| Worker | Units produced | Piece rate (Rs.) | Earnings (Rs.) |
|---|---|---|---|
| A | 240 | 10 | 2,400 |
Unlock everything free for 14 days
- Full step-by-step solutions
- Concept-first explanations
- Methods, shortcuts & mistakes
- PYQ mapping + timed mock tests
Full access for 14 days. No credit card required.