Question 68 of 81

Q.From the following information, calculate the earnings of workers A and B under straight piece-rate system : Normal rate per hour : Rs.1,800
Standard time per unit : 20 seconds Worker A produces 240 units in one hour and Worker B produces 390 units in one hour.

ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2023Subjective· 8mImportance★★★★★est
84% · 68/81 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Piece rate = Rs.10/unit; A earns Rs.2,400 and B earns Rs.3,900 under straight piece-rate.

Step 1 — Find the standard output per hour (standard time per unit = 20 seconds):

  • 1 hour = 60 × 60 = 3,600 seconds.
  • Standard output per hour = 3,600 ÷ 20 = 180 units per hour.

Step 2 — Find the piece rate per unit (normal rate per hour = Rs.1,800):

  • Piece rate = Normal rate per hour ÷ Standard units per hour = 1,800 ÷ 180 = Rs.10 per unit.

Step 3 — Earnings under straight piece-rate (Earnings = Units produced × Piece rate):

WorkerUnits producedPiece rate (Rs.)Earnings (Rs.)
A240102,400

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.