Skip to content
Exercises · Q7

Q.A project has activities A, B, C, D, E with the following predecessors and durations: A (—, 3 days), B (—, 4 days), C (A, 2 days), D (B, 6 days), E (C and D, 2 days). Find the critical path and the minimum project completion time.

Tamil Nadu DgeTextbookSubjectiveImportance★★★★★
12% · 3/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Step 1 — Identify the two paths from start to finish. Since C depends only on A, and D depends only on B, with both C and D feeding into the shared final activity E, there are exactly two paths from the start event to the end event: A→C→E, and B→D→E.

Step 2 — Find the duration of path A→C→E. 3+2+2=73+2+2=7 days.

Step 3 — Find the duration of path B→D→E. 4+6+2=124+6+2=12 days.

Step 4 — Identify the critical path. The critical path is the longest path through the network (the path with zero float throughout), since the project cannot finish before its longest chain of dependent activities is complete. Comparing 77 days (A→C→E) against 1212 days (B→D→E), the longer path, B→D→E, is critical.

Step 5 — State the minimum completion time. The project's minimum completion time equals the critical path's total duration: 4+6+2=124+6+2=12 days. Path A→C→E has 12−7=512-7=5 days of float — it could be delayed by up to 5 days without affecting the overall project finish date. …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.