Q.One of the conditions for the activity (i,j)(i, j) to lie on the critical path is :

(a) Ej−Ei=Lj−Li≠tijE_j - E_i = L_j - L_i \neq t_{ij}
(b) Ej−Ei=Lj−Li=tijE_j - E_i = L_j - L_i = t_{ij}
(c) Ei−Ej=Lj−Li=tijE_i - E_j = L_j - L_i = t_{ij}
(d) Ej−Ei=Li−Lj=tijE_j - E_i = L_i - L_j = t_{ij}
Tamil Nadu DgeTamil Nadu HSC First Year (DGE) Commerce Board 2020MCQ· 1mImportance★★★★★
42% · 11/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Activity (i,j)(i,j) is critical when Ej−Ei=Lj−Li=tijE_j - E_i = L_j - L_i = t_{ij}, meaning it has zero float.

For an activity (i,j)(i,j) with duration tijt_{ij}, let Ei,EjE_i,E_j be the earliest event times and Li,LjL_i,L_j the latest event times of its tail and head nodes.

…

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.