(a) A project schedule has the following characteristics.
| Activity | 1-2 | 1-3 | 2-4 | 3-4 | 3-5 | 4-9 | 5-6 | 5-7 | 6-8 | 7-8 | 8-10 | 9-10 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
OR
(b) Compute Quartile deviation from the following data.
| CI | 10-20 | 20-30 | 30-40 | 40-50 | 50-60 | 60-70 | 70-80 |
|---|---|---|---|---|---|---|---|
| 12 | 19 | 5 | 10 | 9 | 6 | 6 |
Tamil Nadu DgeTamil Nadu HSC First Year (DGE) Commerce Board 2024Subjective· 5mImportance★★★★★
88% · 23/26 Questions
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →(a) The project takes 22 time-units along critical path 1–3–5–7–8–10. (b) The quartile deviation is about 16.11.
(a) CPM
Forward pass (E): Duration .
Backward pass (L):
Activity table ():
| Activity | EST | EFT | LST | LFT | Float | |
|---|---|---|---|---|---|---|
| 1-2 | 4 | 0 | 4 | 5 | 9 | 5 |
| 1-3 | 1 | 0 | 1 | 0 | 1 | 0* |
| 2-4 | 1 | 4 | 5 | 9 | 10 | 5 |
| 3-4 | 1 | 1 | 2 | 9 | 10 | 8 |
| 3-5 | 6 | 1 | 7 | 1 | 7 | 0* |
| 4-9 | 5 | 5 | 10 | 10 | 15 | 5 |
| 5-6 | 4 | 7 | 11 | 12 | 16 | 5 |
| 5-7 | 8 | 7 | 15 | 7 | 15 | 0* |
| 6-8 | 1 | 11 | 12 | 16 | 17 | 5 |
| 7-8 | 2 | 15 | 17 | 15 | 17 | 0* |
| 8-10 | 5 | 17 | 22 | 17 | 22 | 0* |
| 9-10 | 7 | 10 | 17 | 15 | 22 | 5 |
Critical path (zero float): , duration
(b) Quartile deviation …
Unlock everything free for 14 days
- Full step-by-step solutions
- Concept-first explanations
- Methods, shortcuts & mistakes
- PYQ mapping + timed mock tests
Full access for 14 days. No credit card required.