Q.Distinguish between Fixed Cost and Variable Cost, giving two examples of each, and explain how the per-unit amount of each behaves when the level of output changes.
Fixed Cost is a cost that remains constant in TOTAL, for a given period, regardless of the level of output produced, within the normal range of activity. Examples: factory rent, insurance premium on the factory building, and straight-line depreciation of machinery — each of these is a fixed rupee amount for the period whether the factory produces 100 units or 10,000 units.
Variable Cost is a cost that changes in TOTAL broadly in proportion to the level of output. Examples: direct material consumed (more units need more material) and direct labour paid on a piece-rate basis (more units mean more pieces completed, hence more wages).
Per-unit behaviour is where the two costs behave in exactly opposite ways:
- A Fixed Cost's TOTAL is unchanged, so spreading that same total over a LARGER number of units means the cost per unit FALLS as output rises (and, conversely, rises as output falls, since the same fixed total is now spread over fewer units).
- A Variable Cost's TOTAL rises and falls with output, but because it rises/falls in proportion to the very units it is spread over, its cost PER UNIT stays broadly CONSTANT regardless of the volume produced.
| Basis | Fixed Cost | Variable Cost |
|---|---|---|
| Total behaviour | Constant, regardless of output | Changes in proportion to output |
| Per-unit behaviour | Falls as output rises | Broadly constant at any output |
| Example 1 | Factory rent | Direct material |
| Example 2 | Insurance premium / straight-line depreciation | Piece-rate direct labour |
Fixed Cost is constant in TOTAL (e.g. factory rent, insurance premium) but FALLS per unit as output rises; Variable Cost changes in TOTAL roughly in proportion to output (e.g. direct material, piece-rate wages) but stays broadly CONSTANT per unit at any volume.
Unlock everything free for 14 days
- Full step-by-step solutions
- Concept-first explanations
- Methods, shortcuts & mistakes
- PYQ mapping + timed mock tests
Full access for 14 days. No credit card required.