Question 84 of 85
Q.
The following figures relate to two jobs of a manufacturing business :
| Particulars | Job No. 1 (₹) | Job No. 2 (₹) |
|---|---|---|
| Direct Materials | 900 | 1,200 |
| Direct Labour | 600 | 900 |
| Chargeable expenses | 100 | 300 |
Work on cost is 50% on prime cost and office on cost is 10% of work cost. Find out the total cost for each Job.
ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2024Subjective· 8mImportance★★★★★est
99% · 84/85 Questions
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →Prime cost + 50% works on-cost + 10% office on-cost gives Job 1 total ₹2,640 and Job 2 total ₹3,960.
Step 1 — Prime cost = Direct Materials + Direct Labour + Chargeable expenses.
Step 2 — Works on-cost = 50% of prime cost; Works cost = Prime cost + Works on-cost.
Step 3 — Office on-cost = 10% of works cost; Total cost = Works cost + Office on-cost.
Cost Statement for the two Jobs:
| Particulars | Job No. 1 (₹) | Job No. 2 (₹) |
|---|---|---|
| Direct Materials | 900 | 1,200 |
| Direct Labour | 600 | 900 |
| Chargeable expenses | 100 | 300 |
| Prime Cost | 1,600 | 2,400 |
| Add: Work on-cost (50% of Prime Cost) | 800 | 1,200 |
| Works Cost | 2,400 | 3,600 |
| Add: Office on-cost (10% of Works Cost) | 240 | 360 |
| Total Cost | 2,640 | 3,960 |
Workings: …
Unlock everything free for 14 days
- Full step-by-step solutions
- Concept-first explanations
- Methods, shortcuts & mistakes
- PYQ mapping + timed mock tests
Full access for 14 days. No credit card required.