The following figures relate to two jobs of a manufacturing business :

ParticularsJob No. 1 (₹)Job No. 2 (₹)
Direct Materials9001,200
Direct Labour600900
Chargeable expenses100300

Work on cost is 50% on prime cost and office on cost is 10% of work cost. Find out the total cost for each Job.

ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2024Subjective· 8mImportance★★★★★est
99% · 84/85 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Prime cost + 50% works on-cost + 10% office on-cost gives Job 1 total ₹2,640 and Job 2 total ₹3,960.

Step 1 — Prime cost = Direct Materials + Direct Labour + Chargeable expenses.

Step 2 — Works on-cost = 50% of prime cost; Works cost = Prime cost + Works on-cost.

Step 3 — Office on-cost = 10% of works cost; Total cost = Works cost + Office on-cost.

Cost Statement for the two Jobs:

ParticularsJob No. 1 (₹)Job No. 2 (₹)
Direct Materials9001,200
Direct Labour600900
Chargeable expenses100300
Prime Cost1,6002,400
Add: Work on-cost (50% of Prime Cost)8001,200
Works Cost2,4003,600
Add: Office on-cost (10% of Works Cost)240360
Total Cost2,6403,960

Workings: …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.