Q.

Draw the event oriented network for the following data :

Events1234567
Immediate Predecessors-112, 334, 55, 6
Tamil Nadu DgeTamil Nadu HSC First Year (DGE) Commerce Board 2020Subjective· 2mImportance★★★★★
46% · 12/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Draw a node for each event and an arrow from every immediate predecessor into it: 1→2, 1→3, 2→4, 3→4, 3→5, 4→6, 5→6, 5→7, 6→71\to2,\,1\to3,\,2\to4,\,3\to4,\,3\to5,\,4\to6,\,5\to6,\,5\to7,\,6\to7.

This is an event-oriented network construction from the Operations Research (Network Analysis) unit of the Tamil Nadu HSC Class-11 Business Mathematics syllabus.

Step 1 — Read the predecessor table. Each event's "immediate predecessors" tell you which events must complete before it, so an activity arrow points from each predecessor into that event:

  • Event 1: no predecessor — start node.
  • Event 2: predecessor 1 \u2192 arrow 1→21\to2.
  • Event 3: predecessor 1 \u2192 arrow 1→31\to3.
  • Event 4: predecessors 2, 3 \u2192 arrows 2→42\to4 and 3→43\to4.
  • Event 5: predecessor 3 \u2192 arrow 3→53\to5.
  • Event 6: predecessors 4, 5 \u2192 arrows 4→64\to6 and 5→65\to6.
  • Event 7: predecessors 5, 6 \u2192 arrows 5→75\to7 and 6→76\to7. …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.