Q.Draw the logic network for the following : Activities C and D both follow A, activity E follows C, activity F follows D, activity E and F precedes B.

Tamil Nadu DgeTamil Nadu HSC First Year (DGE) Commerce Board 2022Subjective· 2mImportance★★★★★
54% · 14/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Draw an activity-on-arrow network: AA first, then CC and DD from AA's end, EE after CC and FF after DD, EE and FF merging into BB.

This is a network-construction question from the Operations Research chapter of the TN HSC Class-11 Business Mathematics syllabus. We use the activity-on-arrow (AOA) convention and translate each precedence relation into events (circles) joined by activity arrows.

Step 1 — List the precedence relations.

  • CC and DD both follow AA.
  • EE follows CC.
  • FF follows DD.
  • EE and FF both precede BB.

Step 2 — Assign events (nodes).

  • Event 1 = start.
  • A:  1→2A:\;1\to 2.
  • C:  2→3C:\;2\to 3 and D:  2→4D:\;2\to 4 (both burst out of event 2, the head of AA).
  • E:  3→5E:\;3\to 5 and F:  4→5F:\;4\to 5 (both merge into event 5, since both must finish before BB).
  • B:  5→6B:\;5\to 6 (end).

Step 3 — Describe the diagram. …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.