Q.A worker is paid under the Piece Rate system at ₹12.50 per unit. In a day the worker produces 320 units. Compute the worker's wages for that day.

ChseodishaTextbookSubjectiveImportance★★★★★est
6% · 5/81 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Under the Piece Rate system, wages depend only on the number of units actually produced:

Wages = Units Produced × Rate per Unit

= 320 units × ₹12.50

= ₹4,000 …