Q.‘CARO Tech Solutions’ aimed at development of a software system for the company’s growing operations. The project was to be completed within six months with a budget of ₹ 12,00,000. The software development team successfully completed its project on time by outsourcing a part of the project, leading to an additional expense of ₹ 2,00,000. From the following, identify whether the software development team is : (A) Efficient and Effective (B) Efficient but not effective (C) Effective but not efficient (D) Neither efficient nor effective

CBSECBSE Class XII Board 2026MCQ· 1mImportance★★★★★
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

The team completed the project on time (effective) but exceeded the budget (inefficient), so they are effective but not efficient.

To understand this question, you first need to grasp the two distinct ideas that management uses to judge performance: effectiveness and efficiency. These are not the same thing, and a team or organisation can be good at one without being good at the other.

Effectiveness is about doing the right things — it means achieving the stated goal or objective. In this case, the goal was to complete the software system within six months. The team did exactly that. They delivered the project on time. So, from the standpoint of effectiveness, they succeeded. They got the job done.

Efficiency, on the other hand, is about doing things right — it means achieving the goal with the least possible cost or waste of resources. Here, the budget was set at ₹12,00,000. But the team outsourced a part of the project, which added an extra ₹2,00,000. That means the actual cost was ₹14,00,000. They spent more than planned. So, from the standpoint of efficiency, they failed. They did not use their resources optimally.

Note

Outsourcing itself is not a problem — it is a common business practice. The issue is that it led to an unplanned additional expense. If the budget had been revised and approved, the situation might be different. But as per the given facts, the team went over budget.

Now, look at the options:

  • (A) Efficient and Effective — This would require both on-time completion and staying within budget. The team failed on budget, so this is wrong. …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.