Question 40 of 78
Q.Two materials x and y are used as follows:
- Minimum usage - 50 units per week.
- Maximum usage - 150 units per week.
- Normal usage - 100 units per week.
- Ordering Quantity: x - 600 units and y - 1,000 units.
- Delivery period: x - 4 to 6 weeks and y - 2 to 4 weeks.
Calculate for each material:
a) Minimum Level
b) Maximum Level
c) Ordering level.
ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2020Subjective· 8mImportance★★★★★est
51% · 40/78 Questions
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →X: ROL 900, Min 400, Max 1,300. Y: ROL 600, Min 300, Max 1,500.
Formulas
- Ordering (Reorder) Level = Maximum usage x Maximum lead (delivery) time
- Minimum Level = Reorder Level - (Normal usage x Normal lead time)
- Maximum Level = Reorder Level + Reorder Quantity - (Minimum usage x Minimum lead time)
- Normal lead time = (Minimum + Maximum lead time) / 2
Given data
| Particulars | Material X | Material Y |
|---|---|---|
| Minimum usage (units/week) | 50 | 50 |
| Maximum usage (units/week) | 150 | 150 |
| Normal usage (units/week) | 100 | 100 |
| Reorder quantity (units) | 600 | 1,000 |
| Lead time (weeks) | 4 to 6 | 2 to 4 |
| Normal lead time (weeks) | (4+6)/2 = 5 | (2+4)/2 = 3 |
Material X
| Level | Working | Units |
|---|---|---|
| Ordering (reorder) level | 150 x 6 | 900 |
| Minimum level | 900 - (100 x 5) = 900 - 500 | 400 |
| Maximum level | 900 + 600 - (50 x 4) = 1,500 - 200 | 1,300 |
| … |
Unlock everything free for 14 days
- Full step-by-step solutions
- Concept-first explanations
- Methods, shortcuts & mistakes
- PYQ mapping + timed mock tests
Full access for 14 days. No credit card required.