Q.Two materials x and y are used as follows:
  • Minimum usage - 50 units per week.
  • Maximum usage - 150 units per week.
  • Normal usage - 100 units per week.
  • Ordering Quantity: x - 600 units and y - 1,000 units.
  • Delivery period: x - 4 to 6 weeks and y - 2 to 4 weeks.
Calculate for each material:

a) Minimum Level
b) Maximum Level
c) Ordering level.
ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2020Subjective· 8mImportance★★★★★est
51% · 40/78 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

X: ROL 900, Min 400, Max 1,300. Y: ROL 600, Min 300, Max 1,500.

Formulas

  • Ordering (Reorder) Level = Maximum usage x Maximum lead (delivery) time
  • Minimum Level = Reorder Level - (Normal usage x Normal lead time)
  • Maximum Level = Reorder Level + Reorder Quantity - (Minimum usage x Minimum lead time)
  • Normal lead time = (Minimum + Maximum lead time) / 2

Given data

ParticularsMaterial XMaterial Y
Minimum usage (units/week)5050
Maximum usage (units/week)150150
Normal usage (units/week)100100
Reorder quantity (units)6001,000
Lead time (weeks)4 to 62 to 4
Normal lead time (weeks)(4+6)/2 = 5(2+4)/2 = 3

Material X

LevelWorkingUnits
Ordering (reorder) level150 x 6900
Minimum level900 - (100 x 5) = 900 - 500400
Maximum level900 + 600 - (50 x 4) = 1,500 - 2001,300
…

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.