Q.Fill up the blanks :

(xi) Reordering level = Maximum consumption × ________ .
ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2024Subjective· 1mImportance★★★★★est
92% · 72/78 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

The blank is Maximum re-order period (maximum lead time).

The re-ordering (ordering) level is the stock level at which a fresh purchase order must be placed so that stock does not run out before the new supply arrives. To be safe it assumes the worst case — the heaviest usage during the longest delivery time: …