Q.Rectify the underlined portions of the following sentences :

(vii) Time lag between indenting and receiving of the material is called idle time. (underlined portion: idle)
ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2023Subjective· 1mImportance★★★★★est
79% · 62/78 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Correction: "idle" → lead time.

The gap between the moment a purchase order/indent is raised and the moment the material is actually received in stores is the lead time (procurement time). Reorder level is fixed with this lead time in mind so that stock lasts until the fresh supply arrives.

…