Q.Fill in the blank: When single overhead rate is accepted for the industry as a whole, it is called ______ rate.
ChseodishaCHSE Odisha Plus Two (Class 12) Commerce Board 2019Subjective· 1mImportance★★★★★est
24% · 16/67 Questions
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →A single overhead rate used for the whole factory or industry is a blanket (single) rate.
In overhead absorption (a +2 Cost Accounting topic), a blanket rate is one overhead absorption rate computed for the entire factory (or adopted for the industry as a whole), rather than separate departmental rates. It is simple but less accurate, suitable mainly where only one product is made or where all …