Question 10 of 26
Q.The longest path connected by the activities in the network is called :
(a) Solution
(b) Longest duration
(c) Feasible region
(d) Critical path
Puducherry TnboardTamil Nadu HSC First Year (DGE) Commerce Board 2020MCQ· 1mImportance★★★★★
38% · 10/26 Questions
You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.
Start your 14-day free trial to unlock the full solution →The longest path of connected activities through a project network is called the critical path; its length equals the minimum project completion time.
In network analysis (CPM/PERT), a project is drawn as a network of activities. Several chains of activities lead from the start node to the end node. The longest such chain (the path with the greatest total duration) is the critical path, …