Q.Construct the network for the projects consisting of various activities and their precedence relationships are as given below :
A, B, C can start simultaneously A<F,EA<F,E ; B<D,CB<D,C ; E,D<GE,D<G

Puducherry TnboardTamil Nadu HSC First Year (DGE) Commerce Board 2025Subjective· 3mImportance★★★★★
96% · 25/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

Draw start node 1; A: 1-2, B: 1-3; from 2 emerge E, F; from 3 emerge C, D; E and D merge at node 4, then G; C, F, G terminate at end node 5.

Given precedence relations: A, B, C may start together; A<F,EA<F,E; B<D,CB<D,C; E,D<GE,D<G.

Step 1 — identify starting activities.

Activities with no predecessor start from the initial event. From the relations, A and B have no predecessor. (C is shown as a successor of B via B<CB<C; this contradicts the words "C starts simultaneously," so we follow the precedence relations, which are the binding data — see the note below.)

Step 2 — lay out the events (nodes).

  • Node 1 = start event. A and B start here.
  • A: 1→21\to2
  • B: 1→31\to3

Step 3 — place the successors.

  • A<E,FA<E,F: E and F begin after A (at node 2). E: 2→42\to4, F: 2→52\to5.
  • B<D,CB<D,C: D and C begin after B (at node 3). D: 3→43\to4, C: 3→53\to5.
  • E,D<GE,D<G: both E and D must finish before G, so E and D merge at node 4; G: 4→54\to5.

Step 4 — network diagram (event–activity list).

ActivityTail eventHead event
A12
B13
E24
F25
D34
C35
G45
…

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.