Q.One of the conditions for the activity (i,j)(i,j) to lie on the critical path is :

(a) Ej−Ei=Li−Lj=tijE_j-E_i=L_i-L_j=t_{ij}
(b) Ej−Ei=Lj−Li=tijE_j-E_i=L_j-L_i=t_{ij}
(c) Ej−Ei=Lj−Li≠tijE_j-E_i=L_j-L_i\neq t_{ij}
(d) Ei−Ej=Lj−Li=tijE_i-E_j=L_j-L_i=t_{ij}
Puducherry TnboardTamil Nadu HSC First Year (DGE) Commerce Board 2024MCQ· 1mImportance★★★★★
77% · 20/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

The critical-path condition for activity (i,j)(i,j) is Ej−Ei=Lj−Li=tijE_j-E_i=L_j-L_i=t_{ij}.

In network analysis (CPM), for each event we compute the earliest time EE and latest time LL. An activity (i,j)(i,j) with duration tijt_{ij} lies on the critical path when it has no float, which requires all three of these:

  • the events are critical: Ei=LiE_i=L_i and Ej=LjE_j=L_j (zero slack), and …

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.