Q.One of the conditions for the activity (i, j)(i,\ j) to lie on the critical path is :

(a) Ej−Ei=Li−Lj=tijE_j - E_i = L_i - L_j = t_{ij}
(b) Ej−Ei=Lj−Li=tijE_j - E_i = L_j - L_i = t_{ij}
(c) Ej−Ei=Lj−Li≠tijE_j - E_i = L_j - L_i \neq t_{ij}
(d) Ei−Ej=Lj−Li=tijE_i - E_j = L_j - L_i = t_{ij}
Puducherry TnboardTamil Nadu HSC First Year (DGE) Commerce Board 2022MCQ· 1mImportance★★★★★
50% · 13/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

A critical activity has no float, satisfying Ej−Ei=Lj−Li=tijE_j-E_i=L_j-L_i=t_{ij}.

In CPM, an activity (i,j)(i,j) with duration tijt_{ij} lies on the critical path when it has zero total float. The necessary conditions are:

Ei=Li,Ej=LjE_i = L_i,\qquad E_j = L_j

and, for the activity itself,

Ej−Ei=Lj−Li=tijE_j - E_i = L_j - L_i = t_{ij}

…

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.