Skip to content
Question 19 of 26
Q.

(a) A project has the following time schedule.

Activity1-21-62-32-43-54-56-75-87-8
Duration (in days)7614511711418

Construct the network and calculate earliest start time (EST), earliest finish time (EFT), latest start time (LST) and latest finish time (LFT) of each activity, and determine the critical path of the project and duration to complete the project.

OR

(b) Differentiate the function (x−1)(x−2)(x−3)(x2+x+1)\sqrt{\dfrac{(x-1)(x-2)}{(x-3)(x^2 + x + 1)}} with respect to xx.

Puducherry TnboardTamil Nadu HSC First Year (DGE) Commerce Board 2023Subjective· 5mImportance★★★★★
73% · 19/26 Questions
🔒 Locked · start free trial →

You're viewing a preview — the full solution, concept, methods & PYQ mapping are locked.

Start your 14-day free trial to unlock the full solution →

(a) Forward/backward pass gives project duration 36 days and critical path 1–2–3–5–8. (b) Logarithmic differentiation gives dydx=y2[1x−1+1x−2−1x−3−2x+1x2+x+1]\dfrac{dy}{dx} = \dfrac{y}{2}\big[\tfrac{1}{x-1}+\tfrac{1}{x-2}-\tfrac{1}{x-3}-\tfrac{2x+1}{x^2+x+1}\big].

Part (a): CPM network. Activities (with durations): 1-2:7, 1-6:6, 2-3:14, 2-4:5, 3-5:11, 4-5:7, 6-7:11, 5-8:4, 7-8:18.

Forward pass (earliest event times EE):

E1=0, E2=7, E3=21, E4=12, E6=6,E_1=0,\ E_2=7,\ E_3=21,\ E_4=12,\ E_6=6,

E5=max⁡(E3+11, E4+7)=max⁡(32,19)=32,E7=E6+11=17,E_5=\max(E_3+11,\ E_4+7)=\max(32,19)=32,\quad E_7=E_6+11=17,

E8=max⁡(E5+4, E7+18)=max⁡(36,35)=36.E_8=\max(E_5+4,\ E_7+18)=\max(36,35)=36.

Project duration =36= 36 days.

Backward pass (latest event times LL), L8=36L_8=36:

L5=32, L7=18, L3=21, L4=25, L6=7,L_5=32,\ L_7=18,\ L_3=21,\ L_4=25,\ L_6=7,

L2=min⁡(L3−14, L4−5)=min⁡(7,20)=7,L1=min⁡(L2−7, L6−6)=0.L_2=\min(L_3-14,\ L_4-5)=\min(7,20)=7,\quad L_1=\min(L_2-7,\ L_6-6)=0.

Activity times (EST =Ei=E_i, EFT == EST+t+t, LFT =Lj=L_j, LST == LFT−t-t):

ActivityDurESTEFTLSTLFTFloat
1-2707070*
1-6606171
2-3147217210*
2-45712202513
3-511213221320*
4-571219253213
6-7116177181
5-84323632360*
7-818173518361

Zero-float (critical) activities: 1-2, 2-3, 3-5, 5-8.

Critical path: 1–2–3–5–8, duration =7+14+11+4=36= 7+14+11+4 = 36 days.

Part (b): Differentiate y=(x−1)(x−2)(x−3)(x2+x+1)y = \sqrt{\dfrac{(x-1)(x-2)}{(x-3)(x^2+x+1)}}. Use logarithmic differentiation.

…

Unlock everything free for 14 days

  • Full step-by-step solutions
  • Concept-first explanations
  • Methods, shortcuts & mistakes
  • PYQ mapping + timed mock tests

Full access for 14 days. No credit card required.